Construction Update

  • Construction Update - November 2

    Managers: Please post this update in your respective areas.

    Main Building (C) – Laboratory Medicine Renovations 2nd Floor

    • Project Scope: The project consists of multi-phased renovations to various spaces in Laboratory Medicine .   
    • Schedule: Work began late October, with construction scheduled to be completed late summer 2027.
    • Impacts:
      • Construction will occur during normal business hours and during off hours as required to limit patients, visitors, and staff to construction activities.  
      • Please be observant of all posted construction signage and your surroundings. Do not enter construction areas.
      • Construction work will generate intermittent noise. Please contact Andrew Lescoe at 959-710-6558 with any issues.

    Main Building (L) – LM079 – Retail Pharmacy (Outside Cafeteria)

    • Project Scope: The project consists of the renovation of an existing area to create the new Blue Oak Retail Pharmacy.   
    • Schedule: Work began mid-September, with construction scheduled to be completed mid-November 2026.
    • Impacts:
      • Construction will occur during normal business hours and during off hours as required to limit patients, visitors, and staff to construction activities while accessing the Main Building.  
      • Please be observant of all posted construction signage and your surroundings. Do not enter construction areas.
      • Construction work will generate intermittent noise. Please contact David Tice at 860-984-4714 with any issues.

    Main Building (C) – CM185 - Main Entrance Lobby Vestibule Renovation

    • Project Scope: The project consists of the removal of the existing revolving door and replacing it with an expanded entrance vestibule featuring automatic sliding entry doors. Also included is an enhanced patient curbside drop-off zone that will have a continuous curb cut ramp between the existing canopy support columns. This renovation will enhance energy efficiency and increase lobby comfort while improving patient, visitor, and staff safety.   
    • Schedule: Work is on-going, completion scheduled for early February 2027.
    • Impacts:
      • Construction will occur during normal business hours and during off hours as required to limit patients, visitors, and staff to construction activities while accessing the Main Building entrance and patient drop-off areas.  
      • Please be observant of all posted construction signage and your surroundings. Do not enter construction areas. Pedestrian access points into the Main Lobby are expected to shift during various phases as the project progresses.
      • Construction work will generate intermittent noise. Please contact Andrew Lescoe at 959-710-6558 with any issues.

    University Tower (T) – MRI Upgrade and Mobile Unit

    • Project Scope: Install utilities in T SB, B and G to new exterior chiller outside the ED entrance where Bldg.’s F & T meet. Fencing will be installed around the PET CT area; handicap accessible ramp will be installed to the PET CT trailer. Repairs and modifications will be done to the existing procedure canopy. Additional handicap parking spaces will be provided where the grass island is outside the ED entrance.  
    • Schedule: Work to begin late March and run through early-Fall 2026
    • Impacts:
      • Construction will occur during normal business hours. 
      • Be aware of posted signage. Do not enter construction areas.
      • Construction work may generate some intermittent noise. Please contact Andrew Lescoe at 959-710-6558 with any issues.

    Administrative Services Building (D) – ASB Data Center Generator and Power Improvements

    • Project Scope: Upgrade existing power, generator and HVAC improvements to the Data Center
    • Phase 2 to replace generator and the remaining electrical scope of work, starts Winter 2026, completion Spring 2027.
    • Impacts:
      • Construction will mostly occur during normal business hours.
      • Be aware of posted signage. Do not enter construction areas.
      • Construction work may generate some intermittent noise and odors. Please contact Richard Spash at 860-371-7205 with any issues. 

    Transgenic Animal Facility Building (K) – Roof Replacement

    • Project Scope: Replace existing ballasted roof with new EPDM roof. Replace walkway from Parking Lot A2 to the Building E entrance.
    • Schedule: Roof replacement was completed in Fall 2025. Walkway/Bridge replacement will occur from April 6th through Fall 2026. 
    • Impacts:
      • Construction will mostly occur during normal business hours.
      • Certain specific tasks are scheduled on weekends to limit impact on building operations.
      • The Building E entrance from Parking Lot A2 will be closed for safety reasons to allow the bridge/walkway to be removed and replaced.  Signage will be posted directing staff to alternate nearby entrances. 
      • Area 1 parking capacity in Lot A2 will be temporarily reduced by approximately 17 spaces to allow for a construction mobilization area for the walkway replacement.
      • Construction work may generate some intermittent noise and odors. Please contact Janice Hill at 860-480-6392 with any issues.

    CT Tower (H) – Main Level – Interventional Radiology (IR) and Support Areas Renovation

    • Project Scope:
      • Phase 1 - Create a new IR Room, C-Arm Room, Temporary Patient Restroom, Reception/Waiting Room, partial Reading Room and partial IT Closet.
      • Phase 2 – Create a new Changing Room, three permanent Patient Restrooms, Clinical Staff Space, full IT Closet, and Stretcher Holding Area.
    • Schedule: Work on-going, completion Summer 2027.
    • Impacts:
      • Scaffolding has been installed in front of the low roof between C Building and H Building (Connecticut Tower) to facilitate utility work on the roof.  Please maintain a safe distance and be aware of related signage.
      • Construction will occur during normal business hours. Material deliveries and trash removal will occur off hours.
      • Certain specific tasks are scheduled on weekends in order to limit impact in clinical areas.
      • Be aware of posted signage and room closures. Do not enter construction areas.
      • Some corridors may be narrower or temporarily closed due to construction.  Use caution when walking in the area.
      • Main Floor Corridor HM001 leading from Connecticut Tower to University Tower will be temporarily narrowed from 10/26 through 11/4. 
      • Construction work may generate some intermittent noise and odors. Please contact Janice Hill at 860-480-6392 with any issues.

    Replace Main Liquid Oxygen Tanks - West Loading Dock Receiving/A4 Parking Area

    • Project Scope: Provide temporary oxygen tank on trailer until new permanent oxygen tanks are installed. Create new larger tank pad, fenced enclosure and surrounding walkways to accommodate new liquid oxygen tanks.
    • Schedule: Construction work to occur through November 2026.  New tank installation and commissioning will take place in November.
    • Impacts:
      • Limited emergency, courier, vendor vehicle parking and maneuvering.
      • Pedestrians must stay within identified walkways.
      • Be aware of all notifications, barricades, detours, actives and stay clear of the oxygen tank trailer.
      • Area 1 parking capacity in Lot A4 will be temporarily reduced by approximately 30 spaces to allow for construction and installation of the new oxygen system.
      • Please contact Environmental Control Center 860-679-2348 or Janice Hill 860-480-6392 with any issues.

    Kevin R. Norton / Director / Campus Planning, Design and Construction

    For more information, contact: Teresa Dinovellis at 860-679-6511