Managers: Please post this update in your respective areas.
Main Building – B Area – Building Roof Exhauster Sound Attenuators
- Project Scope: Add sound attenuation to roof top exhaust units.
- Schedule: Installation of structural steel is scheduled Saturday, July 31, 2021. Exhaust attenuators are being scheduled for late August pending delivery.
- Impacts:
- Thursday evening, 7/29/21, barricades will be placed in Parking Lot A2 in the handicap parking area next to the Academic Research Building entrance for staging the crane to lift structural steel onto the roof.
- Friday morning, 7/30/21, the crane will be staged in the handicap parking area and crane setup will begin.
- Saturday morning, 7/31/21, crane setup will be completed and lifting of the structural steel will take place. Saturday afternoon the crane will be disassembled and removed from Parking Lot A2.
- The south exit of B Building will closed to pedestrian traffic during crane lifting operations.
- Be aware of construction barricades and signage.
- The sound attenuators are anticipated in late August.
- For more information, contact: Rich Allen at 860-480-2087.
Main Building – F Area – FM022 Diagnostic Imaging Access Control
- Project Scope: Add card readers to staff and patient care areas.
- Schedule: Construction of a new wall and swing door will begin Saturday, July 10, 2021. The work will continue for approximately one week, follow work up with electrical shop is being scheduled.
- Impacts:
- Construction work will be done during non-business hours.
- Be aware of construction barricades and signage.
- Some construction work may generate some intermittent noise and odors.
- For more information, contact: Rich Allen at 860-480-2087.
University Tower (T) – TM112 Office of patient Experience Renovation
- Project Scope: Demolition of millwork, construct two new offices, install two new modular furniture offices, patch floors, paint, modify HVAC distribution and electrical systems.
- Schedule: Construction is expected to be substantially complete by early October 2021.
- Impacts:
- There will be no access through the construction area. Be aware of posted signage. Do not enter construction areas.
- Construction has been scheduled during normal business hours and off hours depending on activities.
- Construction work may generate some intermittent noise and odors. Please contact Kevin Norton at 860-480-99851 to report any issues.
MSI Building (N) - 3rd Floor – N3101 & N3102 X-Ray Replacement
- Project Scope: Remove old X-Ray equipment from N3101 and N3102 and renovate for installation of new X-Ray equipment. Note that only one room will be done at a time, starting with N3101.
- Schedule: Construction will begin Friday night 7/9/21 and is expected to be complete by end of September.
- Impacts:
- Construction will mostly occur during off hours to avoid impacting patient care. Certain activities will occur during regular business hours due to their nature and will be coordinated in advance.
- Be aware of posted signage. Do not enter construction areas.
- Construction work may generate some intermittent noise and odors. Please contact Janice Hill at 860-480-6392 with any issues.
Garage 1 – Deck Sealant Replacement
- Project Scope: Sections of the rooftop level 6 and level 5 of Garage 1 will be closed for resealing.
- Schedule: Garage 1 start date June 28, 2021 and completion week of August 13, 2021.
- Impacts:
- Throughout the project traffic flow on the upper levels of the garage will be altered.
- Be aware of construction vehicles, barricades and signage.
- Staff and students must not park in the patient parking areas and are advised to be cautious.
- UConn Police will be monitoring the area.
- Traffic delays will occur. Please plan accordingly for extra travel time.
- Work may generate some intermittent noise and odors.
- Please contact Tim Cifone at 860-461-9386 to report any issues.
University Tower (T) - TSB102 Sub-Basement IT Room - Additional Power
- Project Scope: Provide additional power to data room TSB102. Install conduits and wiring above corridor ceiling to designated rooms
- Schedule: Work begins May 24th and will completed by July 18th.
- Impacts:
- Crews working above ceiling on ladders in sub-basement corridors. Be aware of posted signage. Do not enter construction areas.
- Construction work may generate some intermittent noise and odors. Please contact Kevin Norton at 860-480-9851 with any issues.
Main Building – L Area – L2030 – Renovation of Microscope Room 202018
- Project Scope: Furnish and Install new VCT flooring, ceiling grid and tile, paint walls and add new supply and return air.
- Schedule: Construction is expected to be substantially complete by July 19, 2021.
- Impacts:
- There will be no access through the construction area. Be aware of posted signage. Do not enter construction areas.
- Construction has been scheduled during normal business hours and off hours depending on activities.
- Construction work may generate some intermittent noise and odors. Please contact Timothy Cifone at 860-461-9386 to report any issues.
Main Building – C Area – CG046A Vestibule Repair – Ground Floor
- Project Scope: Replace doors and vestibule framing and glass with new.
- Schedule: Construction has begun. Tentative completion date week of July 19, 2021.
- Impacts:
- Be aware of posted signage and do not enter construction areas.
- Construction scheduled during normal working and non-working hours pending activities.
- Be aware of posted signage and do not enter construction areas.
- Project Representative to coordinate with staff, if there any changes to the work schedule. Please contact Timothy Cifone at 860-461-9386 to report any issues.
Main Building – L Area – LSB028 NMR Helium Recovery System Installation
- Project Scope: Installation of a helium recovery system serving the NMR suite.
- Schedule: Construction is expected to be substantially complete in August 2021.
- Impacts:
- Do not enter construction areas.
- Construction has been scheduled during normal business hours and off hours depending on activities.
- Construction workers will be accessing dumpsters at the West Dock.
- Construction work may generate some intermittent noise and odors. Please contact Rich Allen at 860-480-2087 with any issues.
Main Building – C Area – C2056/C2009 Lab Med Automated Track Replacement
- Project Scope: Minor room renovations for Transition Room C2009 followed by installation of temporary analyzer equipment. C2056 work consists of replacement of existing core lab automated analyzer track system with minor utility relocations. Work will be performed during normal and off hours.
- Schedule: Transition Room C2009 Completed, Core Lab C2056 to be completed end of October.
- Above ceiling corridor work.
- Construction work may generate some intermittent noise and odors. Please contact Kevin Norton at 860-480-9851to report any issues.
Outpatient Pavilion (S) – Outpatient Building Security
- Project Scope: Installation of security devices, card readers, at points of egress to prevent entry during off-hours.
- Schedule: Final completion and testing by July 30, 2021.
- Impacts:
- Be aware of posted signage and do not enter construction areas.
- Construction scheduled during non-working hours. Majority of the scope will occur on Saturdays.
- Construction has been scheduled during normal business hours and off hours depending on activities.
- Install remaining security devices. Preliminary testing will take place during off-hours.
- Project Representative to coordinate with staff, if there any changes to the work schedule. Please contact Timothy Cifone at 860-461-9386 to report any issues.
MSI Building (N) - Radiology Security
- Project Scope: Installation of security devices, card readers, at points of egress to prevent entry during off-hours.
- Schedule: Tentative completion date August 30, 2021.
- Impacts:
- Be aware of posted signage and do not enter construction areas.
- Construction scheduled during non-working hours. Majority of the scope will occur on Saturdays.
- Construction has been scheduled during normal business hours and off hours depending on activities.
- Project Representative to coordinate with staff, if there any changes to the work schedule. Please contact Timothy Cifone at 860-461-9386 to report any issues.
Connecticut Tower (H) - H1033 Flooring Improvements
- Project Scope: Remove of existing flooring and installation of new vinyl flooring.
- Schedule: Start date July 12, 2021 and completion August 30, 2021.
- Impacts:
- Be aware of posted signage and do not enter construction areas.
- Construction has been scheduled during normal business hours and off hours depending on activities.
- Project Representative to coordinate with staff, if there any changes to the work schedule.
- Construction work may generate some intermittent noise and odors.
- Please contact Timothy Cifone at 860-461-9386 to report any issues.
Thomas P. Trutter / Vice President / Campus Planning, Design, and Construction
For more information, contact: Teresa Titus at 860-679-6511