Campus Information

  • 11/9 Mansfield Road Construction During November

    Be aware that improvements will be made to a portion of the south end of Mansfield Road- from Coventry Road to Gilbert Road – during this month. At least one lane will always be open to traffic during construction, but if possible please select an alternate route during this time.

     

    The schedule is as follows (weather permitting):

    • Weeks of November 9th and 16th: Remove concrete curbing along east edge of road (Mirror Lake side) and replace with granite curb.
    • Week of November 23rd:  Mill top layer of existing asphalt and repave.
    • Week of November 30th: Paint road striping.
    For more information, contact: Mark Phelan/ Facilities Operations at 781-706-4426 mark.phelan@uconn.edu