The contractor will be starting an Early Concrete Pour for the School of Nursing project. The work will start early on Monday, January 19th for the Slab on Deck Concrete Placement at Level 2.
Start time to set-up Pump Truck and Equipment will be 4:30am
Concrete Trucks expect to start rolling in about 5:00am (Approx 10 trucks)
Anticipated completion of concrete pumping by 11:00am
Impact will mainly be within the School of Nursing project fence, with concrete trucks entering/exiting the site at Gate D- along Alethia Drive. Possible concrete truck line-up along Maple Lane for a short window of time, while concrete is being pumped.
For more information, contact: Katherine Viveiros at katherine.viveiros@uconn.edu