Facilities and Transportation

  • 2/15 South Campus Residence Hall- Steam Shutdowns

    As we continue construction, the temporary boilers are installed and we are gearing up to remove the existing steam utilities within the site.  In order to do this, we need to isolate steam valves and perform multiple steam shutdowns that will impact South Campus Buildings.  A separate BEC list notification will be issued with all the details and the buildings being impacted. 

    The anticipated dates and times for the Steam Shutdowns are as follows:  Any updates to this schedule will be published here and in the BEC List Notifications.

    FEBRUARY 15 - starting at 5AM - SHUTDOWN PERIOD 4 HOURS - Buildings impacted ROME, WILSON, ROSEBROOKS,FINE ARTS (incl MUSIC, MUSIC LIBRARY, DRAMA MUSIC) and KNAFE KATTER THEATER, VON DER MADEN RECITAL HALL, SHIPPEE AND BUCKLEY.

    FEBRUARY 16 - starting at 5AM - SHUTDOWN PERIOD 8 HOURS - Buildings impacted ARJONA and SNOW HALL

     

    For more information, contact: Katherine Viveiros at katherine.viveiros@uconn.edu