Managers: Please post this update in your respective areas.
Diagnostic Imaging – Card Access
- Project Scope: Add card readers to selected doors, replace sliding door with a swing door.
- Schedule: Work will be complete in January.
- Impacts:
- New door hardware & device wiring will is in progress.
- Please contact Rich Allen at 860-480-2087 to report any issues.
Parking Area - Lot 4 – Add Lighting
- Project Scope: Install new light pole and luminaire including all necessary electrical work.
- Schedule: Light Pole Base Install – light pole and fixture tentative installation date January 29, 2021.
- Impacts:
- Be aware of posted signage and do not enter construction areas.
- Construction scheduled during normal business hours, Monday through Friday.
- Project Representative to coordinate with staff, if there any changes to the work schedule.
- Construction work may generate some noise and low odors. Please contact Tim Cifone at 860-461-9386 to report any issues
Main Building – C Area – Anatomic Pathology Office Expansion – CG084
- Project Scope: Cosmetic upgrades to existing office space.
- Schedule: Construction process has begun and is expected to be completed by Early - January.
- Impacts:
- Construction scheduled during normal business hours and off hours.
- Be aware of posted signage. Do not enter construction areas.
- Construction work may generate some intermittent noise and odors. Please contact Kevin Norton at 860-480-9851 with any issues.
Garage 1 and 2 – Sealant Replacement
- Project Scope: Remove and Replace Joint sealant and Rubber Membrane Expansion Joint
- Schedule: Project on hold due to weather.
Munson Road 3rd Floor – P3044B Switch Gear Replacement
- Project Scope: Replace the existing ATS with a new closed transition switch. Retrofit existing double doors with new lever style accessible hardware. Install new double hollow metal door and frame. Several Electrical Shutdowns are required.
- Schedule: Project completion by the end of January 2021,excluding one Eversource coordination item.
- Impacts:
- Be aware of posted signage and do not enter construction areas.
- Construction is scheduled during normal business hours and off hours.
- Construction work may generate some intermittent noise and odors.
- Project Representative to coordinate with staff, if there any changes to the work schedule. Please contact Timothy Cifone at 860-461-9386 to report any issues.
Main Building – C Area - Dermatology Renovations – Psoriasis Clinic
- Project Scope: Convert former emergency department located in the C/Main Building, Main Level to the new UConn Dermatology Psoriasis Clinic.
- Schedule: Millwork, Wall, Ceiling and floor finishes are being installed. Construction is expected to be complete by end of -January.
- Impacts:
- Construction scheduled during normal business hours and off hours.
- Be aware of posted signage. Do not enter construction areas.
- Construction containers and dumpsters will be placed in M2 Parking Lot.
- Construction work may generate some intermittent noise and odors. Please contact Kevin Norton at 860-480-9851 with any issues.
Main Building – L Area – 3rd Floor Renovation
- Project Scope: Renovate L Building 3rd area between the Academic Elevators and the Connecticut Tower Elevator Lobby
- Schedule: Wall and Ceiling systems are being installed. Construction is expected to be substantially complete in April 2021.
- Impacts:
- There will be no access through the construction area. Be aware of posted signage. Do not enter construction areas.
- Construction has been scheduled during normal business hours and off hours depending on activities.
- Construction workers will be accessing dumpsters at the West Dock.
- Construction work may generate some intermittent noise and odors. Please contact Rich Allen at 860-480-2087 with any issues.
Security Camera and Blue Phone Upgrades
- Project Scope: Repair of Blue Phones and ongoing camera repair as needed.
- Schedule: Miscellaneous blue phone and camera repair ongoing.
- Impacts:
- Be aware of posted signage, cones and do not enter construction areas.
- Construction scheduled during normal business hours, Monday through Friday.
- Project Representative to coordinate with staff, if there any changes to the work schedule.
- Construction work may generate some noise and low odors. Please contact Timothy Cifone at 860-461-9386 to report any issues.
S Building – Outpatient Building Security
- Project Scope: Installation of security devices, card readers, at points of egress to prevent entry during off-hours.
- Schedule: Construction start up January 2021.
- Impacts:
- Be aware of posted signage and do not enter construction areas.
- Construction scheduled during non-working hours. Majority of the scope will occur on Saturdays.
- Work will take place during non-patient hours, weekends, non-impact to patients and/or staff. Crews will connect wiring to security panels and install remaining security devices.
- Project Representative to coordinate with staff, if there any changes to the work schedule.
- Construction work may generate some noise and low odors. Please contact Timothy Cifone at 860-461-9386 to report any issues.
N Building - MSI Radiology Building Security
- Project Scope: Installation of security devices, card readers, at points of egress to prevent entry during off-hours.
- Schedule: Construction start up January 2021.
- Impacts:
- Be aware of posted signage and do not enter construction areas.
- Construction scheduled during non-working hours. Majority of the scope will occur on Saturdays.
- Work will take place during non-patient hours, weekends, non-impact to patients and/or staff. Crews will prep and install security devices in stairways.
- Project Representative to coordinate with staff, if there any changes to the work schedule.
- Construction work may generate some noise and low odors. Please contact Timothy Cifone at 860-461-9386 to report any issues.
Main Building – C Area – Caulking Repairs
- Construction Activities Postponed due to COVID-19.
CT Tower - H1 Flooring Improvements
- Construction Activities Postponed due to COVID-19.
Thomas P. Trutter / Vice President / Campus Planning, Design, and Construction
For more information, contact: Teresa Titus at 860-679-6511