Additional UConn Information

  • 10/13 Communication Sciences Bldg.-Central Heating

    Existing boilers in David C. Phillips Communication Sciences Bldg. require replacement, due to unforeseen conditions the boilers (2) will need to be completely removed prior to installing the new units.

    Demolition of the existing boilers will start Thursday, 10/13 and the building will lose the use of the central heating system.  Fac Ops will provide temporary electric heating units to help mitigate the lack central heating.  The central heating system will be back online Friday, 10/21. 

     

     

    For more information, contact: Sunnie Singh/Fac Ops at (408) 393-0890